Integer Preemption Problems

2014

A fundamental assumption in the basic RCPSP is that activities in progress are non-preemptable. Some papers reveal the potential benefits of allowing activity interruptions in the schedule when the objective is the makespan minimization. In this chapter we consider the Maxnint_PRCPSP in which it is assumed that activities can be interrupted at any integer time instant with no cost incurred, that each activity can be split into a maximum number of parts, and that each part has a minimum duration established. We show how some procedures developed for the RCPSP can be adapted to work with the Maxnint_PRCPSP and we introduce some procedures specifically designed for this problem. Furthermore, p…

Mathematical optimizationWork (electrical)Job shop schedulingComputer sciencePreemptionWork contentMinificationSchedule (project management)Duration (project management)Integer (computer science)